If 8 workers can build a house in 20 days, how many workers are needed to build the house in 4 days?
A- 12
B- 26
C- 32
D- 40
E- 44
The Absolute Best Book to Challenge Your Smart Student!
The correct answer is D.
Keep in mind that the number of workers and the number of days are inversely proportional. It means that with more workers, it takes less time to build a house.
First, find the constant. W (number of workers) × D (days) = 8 × 20 = 160
Then, W × 4 (days) = 160 → W = 40
40 workers are needed to build the house in 4 days!The Absolute Best Books to Ace Algebra
Original price was: $29.99.$19.99Current price is: $19.99.Original price was: $29.99.$14.99Current price is: $14.99.Original price was: $29.99.$14.99Current price is: $14.99.Satisfied 1 StudentsOriginal price was: $24.99.$14.99Current price is: $14.99.Satisfied 92 StudentsOriginal price was: $24.99.$15.99Current price is: $15.99.Satisfied 125 Students
Related to This Article
More math articles
- How to Prepare for the TSI Math Test?
- 4th Grade PSSA Math FREE Sample Practice Questions
- A Comprehensive Guide to the SAT Test in 2024
- 10 Most Common 5th Grade MEAP Math Questions
- Full-Length TABE 11 & 12 Math Practice Test-Answers and Explanations
- How many Questions Are on the STAAR Test?
- Can You Cheat on the ALEKS Test?
- Best Note-Taking Tablet for College Students
- What Happens If You Don’t Pass the STAAR Test?
- How to Multiply two Binomials Using Algebra Tiles?
What people say about "Algebra Puzzle – Challenge 32 - Effortless Math: We Help Students Learn to LOVE Mathematics"?
No one replied yet.